Checking with Test Equipment

A complete check of the Smart Motor Manager’s components can be performed with the test
unit and a 3-phase current source.

Test Unit

With the test unit, all protective functions set on the Smart Motor Manager can be checked,
including the pickup levels and tripping delays.

Test with 3-Phase Current Source

Using a 3-phase current source, the main circuit, any primary current transformer, and the
current detection module, Cat. No. 825-MCM, can be tested.

Because the functions of the Smart Motor Manager have already been checked with the test
unit, it is sufficient to supply a current of 1 x I

e

(after approximately 60 min. the thermal

utilization reaches 83%). As an alternative, you can measure the 3-phase currents exactly and
compare the readings with the values indicated by the LCD on the Smart Motor Manager.

Figure 7.1 Test with a 3-Phase Current Source

ATTENTION

!

This test should be performed only by qualified personnel.

825-MCM

825-M

1

3

5

2

4

6

A

M

3 ~

3-phase

,

e

,

e

Measurement of phase currents

Connections
(if current < rated motor current: