Functions 3-38

Publication 825-UM001B-EN-P January 2001

Table 3.T Warm Start Setting Parameters

Emergency Override of Thermal Trip (Emergency Start)

Suggested Procedure

Procedure when PT100 and PTC are not used:

1. Momentarily bridge terminals Y11-Y12 (voltage-free contact). A spring return key

switch is recommended.

2. LCD flashes “EMERGENCY START”.

3. If the thermal release has tripped, it can now be reset.

4. If the maximum number of starts per hour has been reached, the counter has one

start deducted.

5. Start the motor.

6. As soon as the motor starts, the stator winding memory will be set to zero (copper

losses only).

Function

Factory setting

Off

Tripping Time from Warm State as a Percentage of Tripping Time from Cold State

Setting

Setting range

50…100%

Factory setting

70%

Setting steps

10%

Minimum Time Between Two Warm Starts

Setting

Setting range

4…60 min.

Factory setting

60 min.

Setting steps

1 min.

ATTENTION

!

Do not leave Y11-Y12 bridged, because each start will reset the
copper memory