Commissioning Procedure

Preliminary Set-Up

A.

Ensure the work area is clean and tidy. Pathways to main disconnect and
emergency stop push-button must be clear and unobstructed.

B.

The following test equipment is to be prepared for use:

Test power supply, supplied with each controller

Multimeters

Hi-Pot Tester (recommended) or Megger

Oscilloscope with memory (optional)

C.

Complete drawing package and parts list.

D.

Specification of project.