Rockwell Automation Publication 7760-UM001D-EN-P - October 2014

53

Commissioning Procedure

Chapter 2

Figure 28 - Connection for Gate Driver Board

Resistance Checks and Power
Supply Tests

1.

Isolate incoming power to the Incoming Line Unit and, if provided close
Earthing Switch in the Bypass Unit.

2.

Open the doors providing access to the SCR Power trucks as detailed
below. Open the Phase ‘U’ SCR Power Truck Door first, open ‘V’ and ‘W’
phase next as they are interlocked. For re closing operation the operation
sequence is the reverse.

3.

The SCR Power Trucks have to be isolated from Main Power and control
before racking out. The SCR Power trucks are to be racked out to carryout
the Power Supply Test and Resistance Checks.

4.

The Main Power connection of the SCR Power Truck to the Bus is by
copper flexible link to the first and last SCR of the series connections of
SCR in the SCR Power Truck.

Figure 30

shows the Mechanical

connections to bolt the truck in position and the Electrical connections.
Refer to Installation Instructions (Publication

7760-IN001B-EN-P

) for

instructions on removing the SCR Power trucks.

J2

TP1

TP2

J6

RX1

RX2

TP3

TP4

J1

J4

J3

J2

TP1

TP2

J6

J4

J3

Gate signal

fibre optic

receiver

Plug-in test

power supply

Current loop CT

connector

Snubber

terminal

Cathode

terminal

Common test

point

+20V test point

Temperature signal
fibre optic transmitter

Yellow LED

+5V test point

Thermistor
connector

Gate/cathode
connector

Overvoltage
sense terminal

ATTENTION: Servicing energized industrial control equipment can be
hazardous. Severe injury or death can result from electrical shock, burn, or
unintended actuation of controlled equipment. Before proceeding, ensure that
all sources of power are isolated and locked out. Verify that all circuits are
voltage free using a hot stick or appropriate voltage measuring device. Any
covers or barriers removed during this procedure must be replaced and securely
fastened before energizing equipment. Where appropriate, the case of test
equipment should be connected to ground.