2.12

Installation Checklist

-

All packing materials and restraints have been removed from each cabinet.

-

Each cabinet in the Parallel Capacity/Redundant system is placed in its installed

location.

-

A ground bond is installed between any cabinets that are bolted together.

-

All switchboards, conduits, and cables are properly routed to the SSBM, UPMs and

auxiliary cabinets.

-

All power cables are properly terminated.

-

A ground conductor is properly installed.

-

If neutral connection is used, no other N---G bonds exist downstream from the UPMs.

-

Battery cables and harness are terminated on E4 and E5.

-

Internal battery cabinet connections have been completed (bus bars, plugs, etc.).

-

Shunt trip signal wiring is connected from UPMs to battery breaker(s).

-

Air conditioning equipment is installed and operating correctly.

-

The area around the installed Parallel Capacity/Redundant system is clean and

dust-free. (It is recommended that the Parallel Capacity/Redundant system be

installed on a sealed concrete pad or a sealed concrete floor.)

-

Adequate work space exists around the SSBM, UPMs and other cabinets.

-

Adequate lighting is provided around the Parallel Capacity/Redundant system.

-

A 120VAC service outlet is located within 25 feet of the Parallel Capacity/Redundant

system.

-

All circuit breaker trip units settings have been completed per the user’s coordination

study.

-

Each Remote Monitor Panel (RMP) is mounted in its installed location. (OPTIONAL)

-

The control wiring for each RMP is terminated inside the UPS cabinet. (OPTIONAL)

-

The Remote Emergency Power Off (EPO) device is mounted in its installed location

and its wiring terminated inside the SSBM. (OPTIONAL)

-

Summary alarms and/or building alarms are wired appropriately. (OPTIONAL)

-

A Relay Interface Module (RIM) is mounted in its installed location and its wiring is

terminated inside the SSBM. (OPTIONAL)

-

A remote battery disconnect control is mounted in its installed location and its wiring is

terminated inside the UPS and battery cabinet. (OPTIONAL)

-

Startup and operational checks performed by authorized service personnel.