8 to use the load off pushbutton, 9 resetting the upm after load off, 10 using the ssbm emergency upm off pushbutton – Powerware 9315s User Manual

Page 96

Advertising
background image

10--6

Powerware 9315 Parallel Capacity/Redundant System with PHP SSBM

164201373 Rev. A

092402

10.2.8 To Use the LOAD OFF Pushbutton

1.

Raise the clear plastic shield covering the red

LOAD OFF pushbutton on the

UPM Monitor Panel.

2.

Press the

LOAD OFF pushbutton.

The breaker and contactors open (you can hear them opening). The

CB1 switch

trips, and the Load Off

PUSH TO RESET pushbutton on the UPM Control Panel pops

out. The UPM shuts down.

10.2.9 Resetting the UPM after LOAD OFF

CAUTION:

Do not attempt to restart the UPM after Load Off until the cause of the

emergency has been identified and cleared.

The Load Off

PUSH TO RESET pushbutton is a small white button on the UPM

Control Panel. The

PUSH TO RESET pushbutton pops out and the CB1 switch

trips when the LOAD OFF pushbutton on the Monitor Panel is activated.
To reset the UPM:

1.

Press the Load Off

PUSH TO RESET pushbutton until it clicks in and remains

recessed.

2.

Move the

CB1 switch from the center (tripped) position to OFF. The switch

should be difficult to move from the

TRIPPED position.

3.

The UPM is now reset. To restart the UPM , follow the procedure in Chapter 4,

“Starting and Stopping the UPS” in the applicable Powerware 9315 UPS

Operators manual provided with the UPM.

10.2.10 Using the SSBM EMERGENCY UPM OFF Pushbutton

An SSBM Emergency UPM Off is initiated by the covered, red

EMERGENCY UPM

OFF pushbutton on the SSBM Control Panel. This pushbutton is protected by a

clear plastic shield to prevent accidental activation. In an emergency, you can

press this pushbutton to instantaneously control the UPM and SSBM output. The

SSBM

EMERGENCY UPM OFF pushbutton functions differently, depending on the

Emergency Power Off (EPO) option specified when ordered. The options available

are as follows:

S

The critical load is transferred to bypass and UPMs powered down.

UPM CB1 breakers remain closed.

S

Power to the critical load is de-energized and UPMs powered down.

UPM CB1 breakers remain closed.

S

The critical load is transferred to bypass and UPMs powered down.

UPM CB1 breakers trip and the UPM is cut off from utility power.
This function requires additional EPO kit available from Powerware.

S

Power to the critical load is de-energized and UPMs powered down.

UPM CB1 breakers trip and the UPM is cut off from utility power.

This function requires additional EPO kit available from Powerware.