Powerware 9315s User Manual

Page 49

Advertising
background image

6--3

Powerware 9315 Parallel Capacity/Redundant System with PHP SSBM

164201373 Rev. A

092402

4.

Connect the SCM wiring to the terminal block using the terminations shown in

Table 6---1.

Table 6---1. Supervisory Contact Module Wire Terminations

From SCM A

To SSBM

Remarks

TB1---4

TB3---1

TB1---5

TB3---2

TWISTED WIRES (4)

1 2 TURNS PER

TB1---6

TB3---3

1---2 TURNS PER

3 INCHES

TB1---7

TB3---4

From SCM B (if used)

To SSBM

Remarks

TB1---4

TB3---5

TB1---5

TB3---6

TWISTED WIRES (4)

1 2 TURNS PER

TB1---6

TB3---7

1---2 TURNS PER

3 INCHES

TB1---7

TB3---8

5.

Contact your local field service office for verification and testing of the SCM

and its connections prior to making connections to terminal strip TB2 shown

in Figures 6---1 and 6---3.

6.

Repeat steps 1 through 5 for each SCM you are installing.

7.

If you are installing an RMP or RIM in addition to an SCM, proceed to

Chapter 4 or 5, respectively; otherwise, secure the SSBM by reversing the

steps contained in procedure “To Prepare the SSBM for Wiring to an RMP,

RIM, SCM, or Remote EPO” of Chapter 2.