4-10 Commissioning

7000A-RM001A-EN-P – January 2011

7000 “A” Frame


IMPORTANT NOTE FOR COMMISSIONING ENGINEER


The COMMISSIONING ENGINEER is advised to go through this commissioning package and follow
the steps outlined herein to commission PF7000 drive(s). It is the responsibility

of the commissioning

engineer to complete all datasheets included in this package and collect any other relevant information
that may not have been included in the package. Important guidelines for capturing waveforms are also
included in the package for quick reference. These must be reviewed and followed properly by the
commissioning engineer. Anything that is not clear, please contact MV Tech Support for assistance:

Phone: 519-740-4790

Option 1 for technical and option 4 for commissioning questions

[email protected]

or

[email protected]


After successful commissioning of the drive, the commissioning engineer is required to return the
completed commissioning package along with his field service reports to the project manager within one
week after completion of job. If job is not completed and some data collected it must be sent to project
manager within one week after leaving the site. The items listed below MUST be included when
submitting the commissioning package.

1.

All checklists and tables in this document (commissioning checklist, customer data, motor data,

daily service summary, etc.)

2.

Harmonics waveforms must be captured on AFE drives under drive-not-running and full-load

conditions

3.

DC current test waveforms (dc voltage and dc current) and variables while running DC test

4.

Load Test waveforms (line and load voltage and current waveforms at 50% and 100% load or

whatever maximum load and speed allowed by the customer)

5.

Final drive parameter settings and variables (running motor at max speed and load) captured at

SERVICE LEVEL ACCESS.

6.

Modified PLC program (if applicable)

7.

Synchronous transfer waveforms (for synchronous transfer applications)

8.

Marked-up drawings

9.

Summary of issues/failures encountered during commissioning


It must be ensured that all documents and data files (waveforms, parameter settings, variables, trend
data, etc.) submitted by the commissioning engineer are properly named, labeled and organized.

NOTE: It should be noted that if the commissioning datasheets submitted by the commissioning engineer
are incomplete and/or the required commissioning data, such as harmonic waveforms, dc test waveforms,
sync xfer waveforms etc, are not captured correctly or the required data is missing, then it can delay the
processing of expense invoices submitted by the engineer.

IMPORTANT:

While the FSE is still at the site, he MUST send the following information to MV Tech

Support for review via e-mail at

[email protected]

.

• Drive setup after completing the auto-tuning

• Drive variables captured in running condition (at load or no load or uncoupled or with load)

• Line voltage and line current waveforms for harmonics on AFE drives when drive is

energized.