Rockwell Automation 7000A PowerFlex Medium Voltage AC Drive - Air-Cooled (A Frame) User Manual

Page 169

Advertising
background image


Commissioning 4-15

7000 “A” Frame

7000A-RM001A-EN-P – January 2011

PowerFlex 7000 “A” and “B” Frame Drive Commissioning Check List

Pre-Power Tests

Inspect cabinets for debris (tools, hardware, metal shavings, etc.).
Re-install control fuses (to be done with control power off).

Power Tests

Verify that line voltage is at rated value.
Perform a phasing check (18-pulse drives only).
Verify input line harmonic by checking line voltage and current waveforms

at ACB board (only for AFE rectifier drive). Save the waveforms.

Perform IDC Test and verify dc current and voltage waveforms
Autotune

the

drive

Review parameters settings for operating the drive with unloaded motor
Program the drive for operation at full load
Run the drive at rated load and rated speed, and record variables.

Medium Voltage
Tests

Capture line side and load side voltage and current waveforms under running

condition.

Print

DRIVE SETUP, which gives all parameters, firmware revisions, PLC

links, etc.

Complete the Commissioning Datasheets.
Mark up EDs with modifications or corrections done in the control circuit
Add revision notes to modified PLC program.
Have the customer sign sign-off documents.
Provide customer with parameter settings, marked-up drawings,

commissioning package, PLC program and Field Report.

Paperwork

Forward Waveforms, PLC program, modified drawings, Commissioning

Package and Field report to Medium Voltage Support group.

Advertising