8. 42" Head Platform Left Hand Drive
60
PNEG-1842 42"-48" Bucket Elevator Platform and Ladder “X” Series
Decking Section: Up-Leg Hatch Side
1. Install three (3) planks of decking (HSP42008X) on the hatch side at the up-leg end. NOTE: Be sure
to install this section of decking by starting at the inside next to the toe board and working outward.
2. Fasten the decking to the support channels (HSP42032X and HSP42012X) using 5/16" x 1" flange
bolts (S-7470) and 5/16" flange nuts (S-3611).
Install Third Cross Support Channel
1. Install the 40" support channel (HSP4248HS) to the end of the decking planks (HSP42008X) and the
bottom of the toe board (HSP42018X) using 5/16" x 1" flange bolts (S-7470) and 5/16 flange nuts
(S-3611).
Figure 8J