9. 48" Head Platform Right Hand Drive

PNEG-1842 42"-48" Bucket Elevator Platform and Ladder “X” Series

83

Install Toe Boards

1. Install the longest toe board assemblies (HSP42015X and HSP48042X). Orient toe boards so the

(HSP42015X) is towards the up-leg end of the lower head.

2. Fasten toe boards to the support channels using 5/16" x 1" flange bolts (S-7440) and 5/16" flange

nuts (S-3611).

3. Install each end of the long “Z” toe board assembly to the bottom of the long toe board assemblies

using 5/16" x 1" flange bolts (S-7440) and 5/16" flange nuts (S-3611).

4. Install the “Z” toe board (HSP48037X) on the drive side at the down-leg end. Fasten to the ends

of the toe boards (HSP42015X and HSP42018X) using 5/16" x 1" flange bolts (S-7440) and
5/16" flange nuts (S-3611).

5. Install the “Z” toe board (HSP48036X) on the hatch side at the down-leg end. Fasten to the ends

of the toe boards (HSP42015X and HSP42018X) using 5/16" x 1" flange bolts (S-7440) and
5/16" flange nuts (S-3611).

(See Figure 9N.)

Figure 9N