9. 48" Head Platform Right Hand Drive

88

PNEG-1842 42"-48" Bucket Elevator Platform and Ladder “X” Series

Attach Intermediate Handrails to Posts

1. Cut 18" off the tube end of one small intermediate handrails (LDR-4088) and one large intermediate

handrails (LDR-4087). Install these intermediate rails on the drive side next to the lower head.

(See Figure 9S.)

2. Cut 12" off the tube end of one small intermediate handrails (LDR-4088) and one large intermediate

handrails (LDR-4087). Install these intermediate rails on the drive side at the corner.

(See Figure 9S.)

3. Slide the small rail into the large rail and install one set at discharge end and other two (2) sets

opposite the discharge end on hatch side and adjust to fit.

4. Fasten using 5/16" x 1" flange bolts (S-7470) and 5/16" flange nuts (S-3611).

5. Slide the small rails into the large rails and install all the intermediate handrails around the platform

using 5/16" x 1" flange bolts (S-7470) and 5/16" flange nuts (S-3611).

Figure 9S