8. 42" Head Platform Left Hand Drive

PNEG-1842 42"-48" Bucket Elevator Platform and Ladder “X” Series

65

Install Platform Post

NOTE: Position bolt heads to the inside of the platform.

NOTE: Posts should be finger-tightened only until handrails have been installed. Some “free play” will be

required to property fit the handrails in place.

1. Install platform post to the “Z” toe boards with the flat side to the toe board spacing them as shown

in

Figure 8O

.

2. Fasten middle post to toe boards using four (4) 5/16" x 1" flange bolts (S-7470) and 5/16" flange

nuts (S-3611).

3. Fasten corner posts to toe boards using six (6) 5/16" x 1" flange bolts (S-7470) and 5/16" flange

nuts (S-3611).

Figure 8O