6.5.7 E

MERGENCY OPERATION OF THE UNDERCARRIAGE IN THE EVENT OF MOVEMENTS OF THE

AERIAL PART

During transport the aerial part of the machine can turn, thus loosing alignment.
If this occurs, one of the two EMERGENCY PROCEDURES given below can be used:

A)

Machine re‑alignment:

Open the electric components compartment;

Position the emergency on the electric components box,
withdrawing it from the machine key ring, where it is
lead‑sealed (see photo);

Activate the emergency key by turning it in a
anticlockwise direction and holding it in posi‑
tion (see sticker);

The safety devices BY‑PASS icon will appear on
the remote control display.

Re‑align the machine, controlling it from the basket by acting on the remote control and
giving previous consent using the pedal button.