5.4 GPI/GPO Cables Installation

Figure 51: GPI/GPO Connectors

● Plug one shielded CAT5 or CAT6 cable end into the connector labeled GPI on the

IMS1000 board (Figure 51). Install a ferrite core clamp near the connector closest to the
IMS1000. Refer to Section 2525 for more information on ferrite core clamp installation.

● Plug the other end of the shielded CAT5 or CAT6 cable into whichever automation

controller is available or required.

● Take another shielded CAT5 or CAT6 cable and plug the end into the IMS1000

connector labeled GPO (Figure 51). Install a ferrite core clamp near the connector
closest to the IMS1000. Refer to Section 25 for more information on ferrite core clamp
installation.

● Plug the other end of the shielded CAT5 or CAT6 cable into whichever automation

controller is available or required.

5.4.1 GPI/GPO Pin-Out Information

Figure 52: RJ45 Socket Pin-Out

GPI

GPO