Chapter 3 ups installation plan and unpacking, 1 creating an installation plan, 2 preparing the site – Powerware 9390 UPS 100160 kVA User Manual

Page 23: Environmental considerations, Ups installation plan and unpacking, Creating an installation plan, Preparing the site

Advertising
background image

EATON Powerware

®

9390 UPS (20–80 kVA) Installation and Operation Manual

S 164201603 Rev 2 www.powerware.com

3-1

Chapter 3

UPS Installation Plan and Unpacking

Use the following basic sequence of steps to install the UPS:

1.

Create an installation plan for the UPS system (Chapter 3).

2.

Prepare your site for the UPS system (Chapter 3).

3.

Inspect and unpack the UPS cabinet (Chapter 3).

4.

Unload and install the UPS cabinet and wire the system (Chapter 4).

5.

Install features, accessories, or options, as applicable (Chapters 5 and 6).

6.

Complete the Installation Checklist (Chapter 4).

7.

Have authorized service personnel perform preliminary operational checks and
startup.

NOTE Startup and operational checks must be performed by an authorized Eaton Customer Service
Engineer, or the warranty terms specified on page 15-1 become void. This service is offered as part of the
sales contract for the UPS. Contact your Eaton service representative in advance (usually a two-week notice is
required) to reserve a preferred startup date.

3.1

Creating an Installation Plan

Before installing the UPS system, read and understand how this manual applies to the
system being installed. Use the procedures and illustrations in the following chapters
to create a logical plan for installing the system.

3.2

Preparing the Site

For the UPS system to operate at peak efficiency, the installation site should meet
the environmental parameters outlined in this manual. If the UPS is to be operated at
an altitude higher than 1500m (5000 ft), contact your Eaton service representative for
important information about high altitude operation. The operating environment must
meet the weight, clearance, and environmental requirements specified in Drawing
164201603-2 on page A-3 and size requirements specified on Drawing 164201603-9
starting on page A-57.

The UPS cabinets use forced air cooling to regulate internal component temperature.
Air inlets are in the front of the cabinet and outlets are in the top. You must allow
clearance in front of and above each cabinet for proper air circulation. See Table
Table B on page A-4 .

3.2.1

Environmental Considerations

The life of the UPS system is adversely affected if the installation does not meet the
following guidelines:

S

The system must be installed on a level floor suitable for computer or electronic
equipment.

S

The system must be installed in a temperature and humidity controlled indoor area
free of conductive contaminants.

Failure to follow guidelines may void your warranty.

Figure

Advertising