2.4 Putting into operation

2.4.1

Switching on the IDEC SmartRelay/Power On

IDEC SmartRelay does not have a power switch. The

reaction of IDEC SmartRelay during startup depends on the

following:

• Whether a circuit program is stored in IDEC SmartRelay

• Whether a memory cartridge or combined memory/

battery cartridge is inserted

• Whether this is an IDEC SmartRelay version without

display unit (FL1E-B12...)

• The status of IDEC SmartRelay at the time of power

failure.

All possible reactions of IDEC SmartRelay are described on

the following page.
To ensure that the expansion module on IDEC SmartRelay

changes to RUN mode, check the following:

• Has the sliding contact between IDEC SmartRelay and

the expansion module snapped into place properly?

• Is the power supply connected to the expansion module?

• In addition, always ensure that you switch on the power

supply to the expansion module first before activating the

power supply to the IDEC SmartRelay base module (or

activate both power supplies at the same time); if you do

not do this, the system does not detect the expansion

module when you start up the IDEC SmartRelay base

module.

Note

After power-up, the FL1E performs initialization. After completing
initialization, the FL1E is ready to start to run. During initialization,
a sandglass is displayed on the CPU module with display, or the
LED is lit red on the CPU module without display.
Initialization time (regardless of expansion module)
When a memory cartridge or a combined memory/battery cartridge
is installed: Max. 10 sec
When a cartridge is not installed or when a battery cartridge is
installed: Max. 9 sec
*The initialization time depends on the program size.