4 setting of tags and addresses, Setting of tags and addresses -3 – Yokogawa YVP110 User Manual

Page 53

Advertising
background image

<9. Configuration>

9-3

IM 21B04C01-01E

Table 9.3

Execution Schedule of the YVP110

Function Blocks

Index

Parameters

Setting (Enclosed is

factory-setting)

269

(SM)

MACROCYCLE_

DURATION

Cycle (MACROCYCLE)

period of control or

measurement. Unit is 1/32

ms. (32000 = 1 s)

276

(SM)

FB_START_

ENTRY.1

AO block startup time.

Elapsed time from the

start of MACROCYCLE

specified in 1/32 ms.

(32000 = 1 s)

278

(SM)

FB_START_

ENTRY.2

..

.

289

(SM)

FB_START_

ENTRY.14

Table 9.4 shows maximum execution time of YVP

function blocks.

Table 9.4

Execution Time of YVP Function Blocks

Block

Name

Execution

time (ms)

Remarks

AO

95

DI

40

PID

120

Available for option /LC1 or /LC2

OS

95

IS

140

Available for option /EE

AR

120

Available for option /EE

For scheduling of communications for combination

with the next function block, the execution is so

arranged as to start after a lapse of longer than

the time above mentioned. In no case should two

function blocks of the YVP110 be executed at the

same time (execution time is overlapped).
Figure 9.3 shows an example of schedule based on

the loop shown in Figure 9.2.

F902.ai

PID

YVP110

Advanced

Valve Positioner

AI

EJA110

Differential Pressure

Transmitter

AO

Figure 9.2

Example of Loop Connecting Function

Block of YVP110 with other instruments

EJA110

AI

YVP110

PID

AO

Function

Block

Schedule

Communication

Schedule

IN

BKCAL_IN

BKCAL_OUT

F0903.ai

OUT

Unscheduled

Communication

Scheduled Communication

Macrocycle (Control Period)

OUT CAS_IN

Figure 9.3

Function Block Schedule and

Communication Schedule

For the case where the control period(macrocycle)

is set to 4 seconds or longer, set the following

interval larger than 1% of the macrocycle.

• The interval between 'the end of block

execution' and 'the start of releasing CD from

LAS'.

• The interval between 'the end of a block

execution' and 'the start of the next block

execution'.

9.4 Setting of Tags and

Addresses

This section describes the steps in the procedure

to set PD Tags and node addresses in the YVP110.

Connect YVP110 with other network devices and

turn on the power of the host and the bus.
There are three states of Fieldbus devices as

shown in Figure 9.4, and if the state is other than

the lowest SM_OPERATIONAL state, no function

block is executed. YVP110 must be transferred to

this state when a tag or address is changed.

UNINITIALIZED

(No tag nor address is set)

Tag clear

Tag setting

INITIALIZED

(Only tag is set)

SM_OPERATIONAL

(Tag and address are retained, and

the function block can be executed.)

Address clear

F0904.ai

Address setting

Figure 9.4

Status Transition by Setting PD Tag and

Node Address

Advertising