Section 4. INITIAL START-UP (“LOCAL” CONTROL)

4.1 PRE-POWER CHECKS

• Verify wires are properly connected
and no erroneous grounds exist.

• Remove all debris removed from the
GPD 503 enclosure. Check for loose
wire clippings.

• Verify all mechanical connections
inside the GPD 503 are tight.

• Verify motor is not connected to load.

For 460V, 15HP (CT) and above only:
Verify that the GPD 503 power voltage
select connector, located at lower left
corner inside drive chassis (see Figure

4-1, A), is positioned correctly for

the input power line voltage. Voltage is
preset to 460V at the factory.
Reposition, if required, to match nominal
line voltage.

For 575V, 15HP and above only: Verify
the GPD 503 power voltage select
connector (see Figure 4-1, B) is
positioned correctly for the input power
line voltage. Voltage is preset to
575/600V at the factory. Reposition if
required.

4-1

FUSE

200V 380V 440V

220/ 400/ 460V
230V 415V

• •

Figure 4-1. Power Voltage Selection in

460V or 575V GPD 503

A. In 460V GPD 503, 15HP (CT) and Above

B. In 575V GPD 503, 15HP and Above