Figure 4-8. tc and ti timing diagram, Figure 4-9. 52 contact designation – Basler Electric BE1-BPR User Manual

Page 85

Advertising
background image

9272000990 Rev J

BE1-BPR Functional Description

4-33

Figure 4-8. Tc and Ti Timing Diagram


An effective Tc setting can only be made if you know when the main contacts and the 52 contacts change

state in the breaker opening cycle. Figure 4=9 shows some 52 contact designations and timing

references that may be found in some manufacturers’ literature. Typically, large variations can be found in

52a/b designs. To obtain the highest arcing time accuracy, the time relationship between the breaker

main contacts opening and the 52 contact changes of state should be measured using a travel analyzer.

Figure 4-9. 52 Contact Designation