Preparing Power-Up Routines

Using This Chapter

Setting Power-Up
Protection

You can configure your controller so that if a power-loss is experienced while
in run mode, the controller does not come back up in run mode. User control
bit S:26/1 defines whether power-up protection (e.g., fault routine) is executed
upon power-up.

Set S:26/1 manually from the Controller Status screen, or latch this bit through
ladder logic.

For Information About:

Go to Page

Setting power-up protection

14-1

Allowing or inhibiting startup

14-2

Defining controller power-up
procedure

14-2

If S:26/1 is

After power loss, the controller

Set (1)

Scans the fault routine before returning to normal program
scan

When set, the controller scans the fault routine once to
completion after the controller recovers from a power loss.
You can program the fault routine to determine whether the
controller’s status will let the controller respond correctly to
logic and whether to allow or inhibit the startup of the
controller.

Reset (0)

Powers up directly at the first rung on the first program file