Turn the upper lift link end over end and mount it

to the bottom hole in the upper link bracket.

NOTE: Turn end over end means that the

hitch point of the link becomes the link point

and vice versa.

Figure 2-204

Put the Category III bushings that are stored on

the drawbar cage storage pin into the ball

swivels, 1, at the upper and lower link hitch

points.

Figure 2-205

1

Add or remove shims, 1, to ensure that the lower

links do not contact the tires when they are free of

the implement.

Reverse these steps to convert from a Category

III to Category IV Narrow.

Be sure that the correct diameter pins are used in

the hitch attaching points. Undersized pins may

break and damage the implement or ball ends.

IMPORTANT: Use the correct diameter pins in

the 3-point attaching links. Category III upper link

pin size: 32 mm (1-1/4) diameter. Lower link pin

size: 37 mm (1-7/16) diameter. Category IVN

upper link pin size: 45 mm (1-3/4) diameter.

Lower link pin size: 50 mm (2) diameter.