5: Performing Functional Tests

The functional test procedures include:

Power-on and front panel functional checks

Voltage mode operation and current mode operation checks.

For information on local operation, see “Local Operation” on page 3-1
for adjusting front panel controls and settings.

Powering the Power Supply On/Off

To power on the power supply:

1.

Ensure that the front panel power switch is in the Off position.

2.

Ensure that the AC line voltage is within operating range.

3.

Connect the line cord to a grounded AC outlet.

4.

Turn the front panel power switch to the On position.

After a short power-on delay,

illuminates on the

output voltage and current displays, followed by

.

After approximately 1 second, the display returns to normal status.

To power off the power supply:

Turn the front panel power switch to the Off position.

will blink on the display. The ALARM LED illuminates.

After a short delay, all lights on the display will not be illuminated.