Installing the Remote Gateway 9150 unit

Powering up the Remote Gateway 9150 unit

As soon as you connect the Remote Gateway 9150 unit to the power source, the
unit begins to power up.

Note: If you are connecting a Remote Gateway 9150 unit to a UPS
(uninterruptible power supply), ensure that the UPS has a minimum of 100
Watts available.

During power up, the following events occur:

!

The Remote Gateway 9150 unit performs a self-test that verifies all critical
functionality.

!

An LED indicator test sequence is performed.

Power-up self-test

During power-up, the Remote Gateway 9150 unit performs a self-test that
verifies all critical functionality, including:

!

RAM memory test

!

EPROM checksum validation

!

Flash checksum validation

!

DSP health

!

interface loopbacks

The power-up cycle also automatically detects if one or more trunk interface or
DSP application modules have been installed. You can configure trunk interface
and DSP application modules using Configuration Manager.

The power-up cycle takes about 60 seconds to complete.