Test timeout, Starting and stopping a test – Paradyne T1 T1 Access Mux 926x User Manual

Page 225

Advertising
background image

Troubleshooting

9-43

9161-A2-GH30-30

April 1998

Test Timeout

A Test Timeout feature is available to automatically terminate a test (as opposed
to manually terminating a test) after it has been running a specified period of
time.

To use this feature, enable the Test Timeout configuration option under the
System Options branch of the menu tree, and set a duration for the test to run in
the Test Duration (min) configuration option (see Table 5-9,

System Options

in

Chapter 5,

Setting Up).

Starting and Stopping a Test

Use this procedure to start and/or abort specific tests. To abort all active tests on
all interfaces, see

Aborting All Tests

on page 9-44.

When the status of a test is . . .

The only command available is . . .

Inactive

Start

Active

Stop

You start or stop an individual test using the same general procedure. For more
specific instructions, see the individual test descriptions in this chapter.

"

Procedure

To start or stop a test:

1. Follow this menu selection sequence:

Main Menu

Test

2. Select a test screen for an interface and press Return. The selected test

screen appears, with the cursor positioned in the Command column of the
first line (available test).

Start or Stop appears in the Command column, and Active or Inactive
appears in the Status column, based upon the test’s current status for that
interface.

3. Select the test you want to start or stop and press Return. The selected test

for the interface changes from Stop to Start, or from Stop to Start, also
changing the status of the test.

4. Press Return again to start or stop the test.

Advertising