Defining the system functionality

Creating an interconnection via the electrical shaft

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

8.14.5.2

Creating/editing/deleting measuring systems

If you open the Project view and select an already existing electrical shaft

, the Workspace

contains the Measuring systems tab in which all the existing measuring systems are shown:

• In the list field all measuring systems that have already been created are shown.
• By clicking the New button, you can, if necessary, create additional measuring systems that

cannot be directly assigned to a drive (e.g. for additional correction-value encoders in the

machine).

• You can delete a measuring system that is no longer needed by selecting a measuring system in

the list field and clicking the Delete button.

• By selecting a measuring system in the list field and clicking the Edit button (or simply by

double-clicking the measuring system in the list field), you open the Measuring system dialog

box in which the data of the corresponding measuring system are shown and can also be edited: