Guardian Co-Deposition Controller Operating Manual

4.6.7 Mains Power

With the power switch OFF, connect the AC mains to the controller power input.
The controller automatically accepts 100-240 V (ac), 50-60 Hz.

NOTE: Observe the power-up sequence described below to avoid power glitches

appearing at the evaporation power supply outputs during startup.

WARNING

Power up in this sequence: (1) Press the power switch on
the Guardian controller. (2) Start the EIES Software.
(3) Turn on the evaporation power supplies.

WARNING

Verify that the power cable provided is connected to a
properly grounded mains receptacle.

WARNING

Maintain adequate insulation and physical separation of
sensor, detector, and I/O wiring from hazardous voltages.