Process

The section is divided into the following phases:

Allow instrument to cool down and disconnect from the mains

Remove and check fuse

Insert fuses

Switch the instrument on again

Note

Please note:

If the fuses trip, please always notify your service office as there may be serious reasons for this.

Only use fuses matching the indicated type and the indicated voltage on the fuse holder. No
fuses with a higher amperage (A) may be used.

Safety instruction

Strictly observe the safety instruction "Replacing fuses" under Warning notes during operation (on
page 24).

Phase 1: Allow instrument to cool down and disconnect from the mains

Proceed as follows:

 Open the "Device parameters" dialog in the operating software by selecting Options > Settings

> Parameters.

 Set the setpoint temperature of the furnaces to 0 °C and confirm by clicking OK.

 Wait 2–3 hours until the instrument has cooled down to at least 55 °C.

 Quit the operating software. Execute the following command: File > Exit.

 Switch off the analyzer and its peripherals.

 Disconnect the analyzer from the mains. Disconnect the power supply plug.

 The instrument is now ready for removal of the fuses.

Fuse holder

The following picture shows a fuse holder from the side: