ADLINK ND-6067 User Manual

Page 248

Advertising
background image

246

1. Configure the brand-new NuDAM module according to the

initialization procedures in section 7.2.

2. The baud rate and check-sum status of the new module

must be identity with the existing RS-485 network. The
address ID must not be conflict with other NuDAM modules
on the network.

3. Power off the NuDAM power supply of the existing RS-485

network.

4. Power off the host computer.
5. Wire the power lines for the new NuDAM with the existing

network. Be careful about the signal polarity as wiring.

6. Wire the RS-485 data lines for the new NuDAM with the

existing network. Be careful about the signal polarity as
wiring.

7. Wire to the input or output devices. Refer to section 7.4 for

illustrations.

8. Power on the host computer.
9. Power on the NuDAM local power supply.
10. Use the NuDAM administration utility to check entire

network.

7.4 Application Wiring for NuDAM

7.4.1 Differential Voltage Input

<ND-6017,ND-6018>

AGND

Differential
Signal
Source

<30V

IN(-)

IN(+)

ADC