With no power to the unit, carefully removed the top cover of the analyzer and check for internal
shipping damage by carrying out the following steps:

1. Carefully remove the top cover of the analyzer and check for internal shipping

damage.

2. Remove the setscrew located in the top, center of the Front panel.

3. Slide the cover backwards until it clears the analyzer’s front bezel.

4. Lift the cover straight up.

5. Inspect the interior of the instrument to ensure all circuit boards and other

components are in good shape and properly seated.

6. Check the connectors of the various internal wiring harnesses and pneumatic hoses

to ensure they are firmly and properly seated.

7. Verify that all of the optional hardware ordered with the unit has been installed.

These are listed on the paperwork accompanying the analyzer.

WARNING – ELECTRICAL SHOCK HAZARD

Never disconnect PCAs, wiring harnesses or electronic subassemblies
while under power.

3.1.1. VENTILATION CLEARANCE

Whether the analyzer is set up on a bench or installed into an instrument rack, be sure to leave sufficient
ventilation clearance.

Table 3-1: Ventilation Clearance

AREA

MINIMUM REQUIRED

CLEARANCE

Back of the instrument

10 cm / 4 in

Sides of the instrument

2.5 cm / 1 in

Above and below the instrument

2.5 cm / 1 in

Various rack mount kits are available for this analyzer. Refer to Section 1.4 of this manual for more
information.

3.2. INSTRUMENT LAYOUT

Instrument layout shows front panel and display, rear panel connectors, and internal chassis layout.

Advertising