Commissioning of the system

7.2

Overview of the commissioning steps

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

The main commissioning steps are listed in the following table:

Step

Activity

Lenze software to be

used

1.

Installing field devices ( 43)

2.

Create a project folder ( 43)

3.

Commissioning the i700 servo inverter ( 44)

»PLC Designer«

Commissioning other Lenze field devices ( 70)

»Enginee

/

»EASY Starter«

4.

Creating a PLC program with a target system (Logic/Motion) ( 71)

»PLC Designer«

5.

Configuring the communication parameters ( 73)

6.

Determining the physical EtherCAT configuration (fieldbus scan) ( 75)

If necessary

Importing missing devices / device description files ( 78)

7.

Creating a control configuration (adding field devices) ( 79)

8.

Creating a task ( 82)

9.

Setting a DC synchronisation ( 87)

10.

Setting SoftMotion parameters ( 92)

Only required for drives with Motion functionality.

11.

Processing EtherCAT I/O mapping ( 95)

Only required for drives that solely have the master functionality (logic bus).

12.

Compiling the PLC program code ( 103)

13.

Logging in on the controller with the »PLC Designer« ( 103)

With the log-in, the fieldbus configuration and the PLC program are loaded into

the Controller.

14.

Starting the PLC program ( 103)