10 optimising control, Optimising control, Optimising control ( 67) – Lenze EtherCAT Controller-based Automation User Manual

Page 67: 7commissioning of the system

Advertising
background image

Lenze · Controller-based Automation · EtherCAT® Communication Manual · DMS 6.4 EN · 04/2014 · TD17

67

7

Commissioning of the system

7.3

Detailed description of the commissioning steps

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

7.3.4.10

Optimising control

The final controller settings are carried out online during commissioning with load on the real

machine.

How to optimise the control system

1. Use the menu command Online Login, or log in on the Lenze Controller with <Alt>+<F8>.

• For this, the PLC program must be error-free.
• By means of the log-in, the PLC program is loaded into the controller. In doing so, any

existing program is overwritten.

2. Press the <F5> function key to start the PLC program.
3. Open the tab Signal flow Chart A and select the display mode (operating mode).

The corresponding signal flow diagram is shown with the current parameter values.