7commissioning of the system – Lenze EtherCAT Controller-based Automation User Manual
Page 91
Advertising

Lenze · Controller-based Automation · EtherCAT® Communication Manual · DMS 6.4 EN · 04/2014 · TD17
91
7
Commissioning of the system
7.3
Detailed description of the commissioning steps
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
3. Select the DC functionality "DC for synchronization" in the device tree for the first slave (DC
master) under the master (Lenze Controller).
• The first slave connected to the master must have DC capability.
• If a slave does not support any distributed clocks, only "DC unused" can be selected here.
4. Also select the DC functionality "DC for synchronization" for all other slave devices which
are to use the DC synchronisation.