background image

7

Commissioning of the system

7.3

Detailed description of the commissioning steps

52

Lenze · Controller-based Automation · EtherCAT® Communication Manual · DMS 6.4 EN · 04/2014 · TD17

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

7.3.4.4

Overview of the commissioning steps

The main commissioning steps are listed in the following table:

Step

Activity

1.

Create a project folder ( 43)

2.

Creating a PLC program with a target system (Logic/Motion) ( 71)

3.

Configuring the communication parameters ( 73)

4.

Determining the physical EtherCAT configuration (fieldbus scan) ( 75)

or

Creating a control configuration (adding field devices) ( 79)

5.

Creating a task ( 82)

6.

Setting a DC synchronisation ( 87)

7.

Checking the wiring ( 54)

8.

Entering motor and controller settings ( 54)

9.

Setting the feedback system for servo control ( 57)

10.

Integrating the L_SMC_AxisBasicControl function block ( 59)

11.

Setting SoftMotion parameters ( 92)

Only required for drives with Motion functionality.

12.

Processing EtherCAT I/O mapping ( 95)

Only required for drives that solely have the master functionality (logic bus).

13.

Compiling the PLC program code ( 103)

14.

Logging in on the controller with the »PLC Designer« ( 103)

With the log-in, the fieldbus configuration and the PLC program are loaded into the Controller.

15.

Starting the PLC program ( 103)

16.

Executing manual control ( 65)

17.

Optimising control ( 67)