138

Rockwell Automation Publication 2097-UM001D-EN-P - November 2012

Chapter 6

Configure and Start Up the Kinetix 300 Drive

Apply Power to the
Kinetix 300 Drive

This procedure assumes that you have wired and configured your Kinetix 300
drive system and your Ethernet/IP interface module.

Follow these steps to apply power to the Kinetix 300 drive system.

1. Disconnect the load to the motor.

2. Determine the source of the drive logic power.

3. Apply mains input power to the Kinetix 300 drive IPD connector.
4. Observe the four character status indicator.

5. Determine the source of logic power.

6. Verify that Hardware Enable Input signal IOD connector pin 29 is at 0V.
7. Observe the status indicator on the front of the Kinetix 300 drive.

To avoid hazard of electrical shock, perform all mounting and wiring of the Bulletin
2097 drive before applying power. Once power is applied, connector terminals may
have voltage present even when not in use.

ATTENTION: To avoid personal injury or damage to equipment,
disconnect the load to the motor. Make sure each motor is free of all
linkages when initially applying power to the system.

If Your Logic Power

Then

Is from (24V DC) back-up power

Apply (24V DC) back-up power to the drive (BP connector).

Is from Mains input power

Apply mains input power to the drive (IPD connector).

Four Character

Status Indicator

Comm Activity
Status Indicator

If the status indicator is

Then

diS

Go to

step 5

Blank

Go back to main

step 2

If Your Logic Power

Then

Is from (24V DC) back-up power

Apply mains input power to the drive (IPD connector)

Mains input power

Go to

step 6

Status Indicator

Condition

Status

Do This

Drive Fault

Off

Normal condition

Observe the Comm Activity, status indicator E.

Steady red

Drive is faulted

Go to

Status Indicators

on

page 127.

Comm Activity

Flashing

Communication is ready

Go to Test and Tune the Axis on

page 139.

Off

No communication

Go to

Status Indicators

on

page 127.