Fan motor

1) Perform the step 1-1 and step 2.

2) Remove the fan motor and the flange nut that fixes

the propeller fan.
• To loosen the flange nut, turn it clockwise.

(Turn it counterclockwise for tightening.)

3) Remove the propeller fan.

4) Remove the connector for fan motor from the

inverter. (control board)

5) Remove the fan motor lead from the fan motor

lead fixing rubber on the through hole of the
parting board.

6) Remove the fixed screws (4 for each) while

holding the fan motor so that it does not drop.

* Notes in assembling fan motor

• Tighten the flange nut in 4.95 N•m (50kgf•cm)
• To prevent the fan motor lead from contacting

the propeller fan, adjust the length of fan motor
lead fixing rubber so that it does not slack.
Attach the fan motor lead fixing rubber to the
parting board so that the projection part is
placed on the refrigerant cycle side.

• Make sure that the reactor body and the fan

motor lead do not contact each other.

• Be sure to bind the removed binding tie by

using the commercially available binding tie.

Note

Fix the fan motor lead to the motor base using a
metal tie so that the fan motor lead does not
contact the propeller fan.

No.

Exchange parts

name

Work procedure

Remarks

Propeller fan

Fan motor
fixing rubber

Fan motor

Fan motor

Inverter

Turn it right to loosen

Flange nut

Propeller fan

Projection/Refrigerant
cycle side

Fan motor connector