5. Remove the retainer and seal, 1, using a slide
puller, 3, with a fabricated end, 2. Install a bolt
through the PTO cover and fabricated puller.
NOTE: The fabricated end, 2, consists of a nut that
fits the puller, 3, with a second nut welded to the first
nut.
6. Pull the shaft and bearing assembly.
106
7. Remove the snap ring, 1, and bearing, 2, from the
shaft, 3.
8. Switch the shaft and reassemble in the reverse
order.
9. Apply a bead of gasket eliminator to the shaft
retainer and reinstall it. Torque the four retaining
bolts to 108 N·m (80 ft.-lbs.).
10. Remove the two long M20 x 120 bolts. Add
thread sealer to the original M20 x 60 bolts and
torque them to 641 N·m (475 ft.-lbs.).