Commissioning

Check before switching on the power supply module for the first time:

ƒ

The wiring for completeness, short−circuit, and earth fault

ƒ

The power connection:
– Mains connection via terminals L1, L2, L3 (X21)
– Connection of the RFI filter / mains choke
– Connection of the brake resistor (internal/external) via terminals BR0, BR1 (X22)
– Polarity of the DC bus voltage supply via terminals +UG, −UG (X22)

ƒ

The control connection (X6):
– Connection of the 24 V supply, GND
– Connection of temperature sensor contact of the external brake resistor or

connection of jumper when using the internal brake resistor to terminals T1, T2.

– Adjustment of wiring to the signal assignment of the control terminals.

ƒ

The communication via the system bus (CAN)