Commissioning

Commissioning steps (overview)
Operation via system bus (CAN) with master control

6

l

64

EDBCSXE040 EN 7.0

6.1.2

Operation via system bus (CAN) with master control

)

Note!

Follow the commissioning steps in the given order!

Setting

Brief description

Detailed

information

Conditions

l

Basic settings completed.

l

C0001 = 0

^ 62

1.

Set baud rate.

l

Setting via DIP switch (S1) or C0351

l

Lenze setting: 500 kbits/s

l

Changes are accepted after
– a "reset node" (e.g. C0358 = 1,

^ 94).

– switching off and on again the low−voltage

supply.

^ 82

2.

Set CAN node address at the power
supply module and at each axis
module.

Each address can be used only once in the
network!

l

Setting via DIP switch (S1) or C0350

l

Lenze setting power supply module: 32

l

Changes are accepted after
– a "reset node" (e.g. C0358 = 1,

^ 94).

– switching off and on again the low−voltage

supply.

^ 82

3.

Set identifier for process data
communication.

Setting via

l

C0353

l

C0354

^ 86

The master sets the system bus (CAN) to the "Operational" status.

4.

If necessary, adapt further codes to
your application.

l

Master/slave operation: C0352

l

Mode for the process data transfer:
– C0360 = 1: cyclic (sync−controlled),

^ 157)

– C0360 = 0: event−controlled/cyclic without

sync (

^ 155)

l

Boot up time/cycle time for process data
transfer: C0356

l

"Node Guarding": C0352, C0382, C0383,
C0384

^ 88

^ 89

^ 90

^ 92

5.

Set input X6/DI2 to HIGH.

If the power supply module is ready for operation,
output X6/DO1 is set to HIGH.

6.

Set input X6/DI1 to HIGH.

Charging is enabled.

7.

Specify control word.

l

Reset bit must be set to "0" in the first
telegram.

l

Transmit control word via CAN word 0.

l

Initialise toggle bit or deactivate monitoring.

^ 95

^ 108

8.

Transmit sync telegram (optional).

Sync telegram will be only received by the power
supply module if C0360 = 1 (

^ 89).

9.

Specify control word.

l

Reset bit (LOW active) must be set to "1" to
switch on the power supply module.

l

Set controller enable bit to "1" if output
X6/DO1 is to be set to HIGH when ready for
operation.

^ 95

10. Transmit sync telegram (optional).

See 8.

After some seconds the earth−fault test is complete and the DC bus is charged.

The power supply module is now ready for operation (status word 1 / bit 0 = 1 (

96)).