3 • Operation and Maintenance

Doc. 065291-01 3/09

57

3.5

Check All Connections

1. Make sure the eluent reservoir is filled and the tubing connecting the reservoir

to the ICS-2100 tubing is securely connected (see

Figure 3-8

).

2. Make sure the eluent generator electrical cable (blue) is connected to the

EGC-1

connector.

3. Make sure the CR-TC electrical cable (black) is connected to the

CR-TC

connector.

3.6

Prime the Pump

1. Verify that the priming valve on the primary pump head (see

Figure 3-9

) is

closed (turned all the way clockwise).

2. Open the waste valve on the secondary pump head by turning the knob one-

quarter to one-half turn counterclockwise. Opening the valve directs the
eluent flow path to waste and eliminates backpressure.

3. Press

Prime

on the Chromeleon Control panel or the ICS-2100 touch screen

HOME

page. Confirm that the waste valve is open by pressing

OK

when the

If you changed eluent or if the eluent lines are dry, prime the lines first
with a syringe before following the procedure below to prime the
pump. See

Section 5.16.1

for instructions on priming the lines with a

syringe.

Figure 3-9. Priming the Pump

Priming Valve

Waste Valve

Primary
Pump Head

Secondary

Pump Head

(open)

(close)