Conduit
Where conduits must be coupled together, bridge the joint with a ground conductor bonded
to the conduit on each side of the joint. Bond the conduits also to the drive enclosure. Use
separate conduits for input power, motor, brake resistors, and control wiring. Do not run

motor wiring from more than one drive in the same conduit.

Armored cable / shielded power cable
The motor cables can be run in the same cable tray as other 460 V power wiring. Control and
signal cables must not be run in the same tray as power cables. Six conductor (3 phases and 3
ground) type MC continuous corrugated aluminum armor cable with symmetrical grounds is
available from the following suppliers (tradenames in parenthesis):

• Anixter Wire & Cable (Philsheath)

• BICC General Corp (Philsheath)

• Rockbestos Co. (Gardex)

• Oaknite (CLX).

Shielded power cables are available from Belden, LAPPKABEL (OLEFLEX) and Pirelli.

Installing the Drive

WARNING! Before installing the AQUAVAR, ensure the input power supply to the
drive is off.

Unpack the Drive

1. Unpack the drive.
2. Check for any damage and notify the shipper immediately if

damaged components are found.

3. Check the contents against the order and the shipping label to verify

that all parts have been received.

Prepare the Mounting Location
The AQUAVAR should only be mounted where all of the requirements
defined “Preparing for Installation” on page 15 are met.

1. Mark the position of the mounting holes. Refer to page 138 for

mounting hole location.

2. Drill the holes.

NOTE! Frame sizes R3 and R4 have four holes along the top.
Use only two. If possible, use the two outside holes (to allow
room to remove the fan for maintenance).

Remove Front Cover
IP 21 / UL Type 1

1. Remove the control panel, if attached.
2. Loosen the captive screw at the top.
3. Pull near the top to remove the cover.

INSTALLATION

(Frames R1-R6)

1