Control technology | EtherCAT communication manual

Commissioning of the system

Overview of commissioning steps

44

L

DMS 3.1 EN 01/2011 TD17

The main commissioning steps are listed in the following table:

Step

Activity

Software used

1.

Installing field devices

( 45)

2.

Creating a project folder

( 46)

3.

Fieldbus scan with the »EtherCAT Configurator«

( 47)

»EtherCAT Configurator«

Fieldbus scan with the »scandf« command line tool ( 51)

Command line tool »scandf«

4.

Inserting devices available on the fieldbus into the »EtherCAT

Configurator« project ( 55)

»EtherCAT Configurator«

Creating the configuration in the »EtherCAT Configurator«

( 56)

5.

Export of EtherCAT configuration

( 67)

»EtherCAT Configurator«

6.

Configuration in the »Engineer«

( 54)

»Engineer«

8.

Configuration in the »PLC Designer« ( 68)

»PLC Designer«

9.

Loading the control configuration onto the IPC ( 78)

»PLC Designer«

10.

Loading the master configuration onto the EtherCAT master ( 79)

»PLC Designer«

11.

Loading and starting the PLC program ( 79)

»PLC Designer«