Commissioning of the system

Detailed commissioning steps

7.2.8.2

Creating a task

How to create a task in the »PLC Designer«:

1. Select the Resources tab:

2. Select Task Configuration:

3. Select the Append Task command from the Task Configuration context menu.
4. Create a new task and make the settings relevant for the respective configuration:

Define the task cycle time. (Example in the screenshot: 1 ms)

Note!

The task cycle time must be identical with the DC cycle time set in the »EtherCAT

Configurator«.