Cross Cutter

Installing and starting up the "CrossCutter" prepared solution



Prepared Solution Servo PLC / ECSxA 1.1 EN

3-135

3.4.5

Starting up length-controlled operation



Caution!

The start-up sequence for length-controlled operation of the prepared solution described below
relates to the parameterisable variant.

Requirements:

The cross-cutter axis servo controller has been parameterised in accordance with the installation and start-up
instructions as described in Chapter 3.4.4.

Control voltage is being supplied to the axis via terminals 59 (+24 V DC) and 39 (0 V) and power via terminals
L1, L2 and L3.

Initial situation:

• No errors are being indicated by the servo axis.

• The servo axis has been enabled.

• The application control and status words have not been customised by amending the values in C4010/0xx and

C4012/0xx.

• Axis homing has been completed successfully.


Start GDC and run a search for the controllers connected to the system bus. GDC will find
the connected controllers. These will include the controller loaded with the
CrossCutter_SPLC_Vxxxxxx for 9300 Servo PLC and CrossCutter_ECS_Vxxxxxx for ECS.

Prepared Solution for 9300 Servo PLC

Prepared Solution for ECS
Double-click the cross-cutter axis drive and read back the parameters from the drive.

Start

Step 1