Product Commissioning

3.

Select the ArmorStart located at node 63, and then click OK. The node
commissioning screen will have the “Current Device Settings” entries
completed. It will also provide the current network baud rate in the “New
ArmorStart Settings” area. Do not change the baud rate unless you
absolutely sure that this value needs to be changed.

4.

Enter the desired node address in the “New Device Settings” section. In
this example, the new node address is 5. Click Apply to apply the new node
address.

5.

When the new node address has been successfully applied, the “Current
Device Settings” section of the window is updated as follows. If an error
occurs, check to make sure the device is properly powered up and
connected to the network.

6.

Click Close to exit the node commissioning tool.

7.

Choose “Single Pass Browse” from the “Network” menu to update
RSNetWorx and verify that the node address is set correctly.