This chapter provides an overview of the setting up process for the AADvance
AADvance Workbench, including creating a new project.

In This Chapter

Create a New Project ....................................................................................... 6-1

Compiler Verification Tool .............................................................................. 6-2
Allocate IP Addresses for Network Communications .............................. 6-4

Configure the IP Address of the Target Controller................................... 6-5

Create a New Project

The configuration process starts by creating a new AADvance project. To create a

new project do the following:

1) Start the AADvance AADvance Workbench.
2) Select File then New Project/Library (<ctrl>+N).

The New dialog box opens.

3) Enter a project name (maximum of 128 characters) and add a comment line.
4) Choose the AADvance_System template from the drop down list, click OK.

The AADvance Workbench creates a project.