PowerFlex “C” Frame Commissioning Checklist

Programming the Operator Interface

Verify preliminary parameter settings.

Calibrate signal conditioners

Set analog outputs

Fault masks / External faults

Analog I/O

PLC In/Out

System Tests

Perform a system test with low voltage control/test power.

Prove all protection functions as desired.

Verify that all emergency stop devices function.

Calibrate the analog I/O.

Test cooling system operation.

Medium Voltage

Tests

Pre-Power Tests

Inspect cabinets for debris (tools, hardware, metal shavings, etc.).

Re-install control fuses (to be done with control power off).

Power Tests

Measure input contactor drop out time. (2-cycle advance warning
needed if input contactor is not part of drive line-up)

Verify that line voltage is at rated value.

Verify harmonic by checking voltage and current waveforms at SCBL
board (PWM only).

Perform a phasing check (18-pulse drives only).

Review drive program settings for operating at reduced load.

Perform an IDC Test.

Autotune

Program the drive for operation at full load.

Run drive at rated load and rated speed.

Capture waveforms of voltages and currents on the line and motor sides.

Paperwork

Print DRIVE SETUP, which gives all parameters, firmware revisions,
PLC links, etc.

Complete the Commissioning Data Sheets.

Mark up modified electrical drawings.

Add revision notes to modified PLC program.

Have the customer sign sign-off document.

Provide customer with parameter settings, marked-up drawings,
commissioning package, PLC program and Field Report.

Forward PLC program, modified drawings, Commissioning Package
and Field report to Medium Voltage Support group.