11-2

The first checks you make are:

ac

power

machine input/output devices

ac Power

Test each component receiving ac power. For each component receiving
ac power, perform the following steps.

1.

Measure the ac line voltage using a volt meter and make sure it
corresponds to the power supply or component. Verify the
incoming power.

2.

Check the wiring of the:

main disconnect switch or circuit breaker
master control relay
emergency stop switches

3.

Check power cable connections. Make sure connections are correct
and secure.

Machine Input/Output Devices

Test each machine input/output device. For each device, use a volt meter
to make sure the devices are receiving the necessary power.

Perform Standalone

Hardware Check