Chapter 11

Checking the Hardware

11-8

4.

To make sure you have wired each I/O correctly, perform a continuity
test for each I/O wired.

To test the vision components, follow the steps below:

1.

Apply power to each vision device and make sure the PASS/FAIL
indicators are GREEN.

If the indicators are not green:

remove

power

make sure the connections are correct and secure
re-apply power and re-check indicators

2.

Check the monitor’s screen. A message similar to the one shown
below should be displayed.

ALLEN-BRADLEY

Configurable Vision Input Module

Bulletin 5370-CVIM

Series xxx Revision X

Copyright 1993 Allen-Bradley Company

Phase I Diagnostics Completed Status = OK

Phase II Diagnostics Completed Status = OK

System Initialization Completed Status = OK

Power-up Completed

17214

If the display is not similar to the one shown above:

remove

power

make sure the connections are correct and secure (see chapter 6)
re-apply power and re-check the monitor’s screen

Check Vision Components