143

The generator voltage should build to a percentage of the rated voltage. (The FCR
setpoint was set to 20% of the rated exciter field current in a previous step.) ...................... ________

Increase the exciter field current to 75% of rated. ................................................................. ________

The generator voltage should build to a percentage of the rated voltage. ............................ ________

Check the field voltage with an oscilloscope to verify proper output. (See the current
balance firing circuit waveform of Figure 103.) ...................................................................... ________

Figure 103. Field Voltage Output Waveform

Meter for the correct voltages at the voltage sensing inputs (E1, E2, E3). ........................... ________

Measure the PPT secondary voltages. (See Table 22 for the correct secondary
voltages at the transformer output.)

Table 22. PPT Secondary Voltages

Rectifier DC Voltage

PPT AC Secondary Voltage

63

80

125

160

250

360

375

480

Using the Raise/Lower control raise the terminal voltage incrementally to the rated
voltage. .................................................................................................................................. ________

Place the Start/Stop switch in the Stop position. ................................................................... ________

Place the Start/Stop switch in the Start position to start the generator in FCR mode. .......... ________

Record the voltage buildup characteristic of the system as it reaches full-rated output. ...... ________

Perform a step response in FCR mode. ................................................................................ ________

Using the BESTCOMS Analysis screen, perform a 5% step change in FCR mode. ............ ________

Decrease the value first, and then increase the value. (Observe stable performance
using the recording capabilities of the Analysis screen.)....................................................... ________

Note the overshoot and settling time. (The FCR output should be very stable.) .................. ________

During the following test, be prepared to transfer back to FCR mode if there is a problem. Use the
BESTCOMS Metering screen to verify that tracking is stable before transferring. The Null Balance
indicator on the front panel should be continuously lit. If pre-position is enabled, the setpoint will go to the
assigned value first. Pre-position may need to be disabled for this test.

Verify that the AVR setpoint follows (auto-tracks) the FCR setpoint, then transfer. ............. ________

Note

During the following test, if pre-position is enabled, the setpoint will go
to the assigned value first.

DECS-400